Updates


road closure information

This page is intended to advise residents, businesses, and the traveling public of the City of Sidney to the Wapakoneta Avenue Reconstruction Project. Phase 2 includes:

 

Phase 2 of the project is located on Wapakoneta Avenue at the intersection with Parkwood Street proceeding south to Russell Road.

Phase 2 is a continuation of Wapakoneta Avenue Reconstruction Phase 1 completed in 2012 which encompassed Parkwood Street north to I-75.

Phase 2 includes removal and reconstruction in order to widen the roadway and add a center-turn lane. Also included are curb & gutter, sidewalk, water main replacement, sanitary sewer replacement.

The approximate physical dimensions of the project include:

Reconstruction
2,628’ of roadway reconstruction
8,029 cy excavation
2,032 cy 7” asphalt base
2,216 cy 6” aggregate base
900 cy asphalt course
18,000 sf 4” sidewalk
5,038’ curb & gutter
25 curb ramps w/ truncated domes

Storm
2,300’ storm pipe of various sizes
15 catch basins
7 manholes
5 yard drains

Sanitary
400’ pipe
3 manholes

Water
2,037’ water main of various sizes
5 hydrants